St Katherine's School: A Collaborative Solar, Battery & Energy Management Solution
Immersa worked alongside SSE Energy Solutions, Activ8 Energies and GridIMP to support the delivery of a new solar and battery storage system at St Katherine's School. The project brought together specialist expertise from across the energy sector. SSE Energy Solutions developed the scheme as part of its Building Management Service, with Activ8 Energies delivering the 218kWp solar PV installation and 30kW / 144.6kWh AlphaESS BESS. Immersa supplied the battery storage system and provided installation support, while GridIMP will deliver advanced optimisation and control of the BESS to help generate greater energy savings and revenue for the school.

Project at a Glance
A four-party collaboration combining 218kWp of new solar PV, a 30kW / 144.6kWh AlphaESS BESS and advanced optimisation within SSE Energy Solutions' Building Management Service.
Immersa's Role:
BESS supply and installation support
Installer:
Activ8 EnergiesScheme Developer:
SSE Energy SolutionsBESS Optimisation & Control:
GridIMPEnd Client:
St Katherine's School
End Customer Type:
Education
Solar PV:
218kWp
Battery Storage:
AlphaESS G3-H30 – 30kW / 144.6kWhAdditional Storage:
72.3kWh Extension Cabinet
Application:
New BESS alongside new solar PV
Project Objective:
Combine solar generation, battery storage and intelligent energy management to reduce energy costs and unlock additional value
Core Benefit:
Four-party collaboration bringing together solar, BESS and advanced optimisation within SSE Energy Solutions' Building Management Service
Challenge
Delivering the greatest value from renewable energy requires more than simply installing solar PV and battery storage. The technologies need to work together effectively, while the battery must be intelligently managed around the site's energy requirements. For St Katherine's School, the project therefore brought together four specialist partners, each responsible for a different element of the overall energy solution. The objective was to create an integrated system that could make better use of renewable generation while using intelligent battery optimisation to increase the financial value delivered to the school.
Approach
- Supplying the AlphaESS G3-H30 battery system
- Supplying a 72.3kWh Extension Cabinet
- Supporting the offloading of the BESS using a HIAB
- Positioning the system in its required location
- Installation support throughout the BESS deployment
- This allowed Immersa to support Activ8 Energies with a key part of the project while working alongside SSE Energy Solutions and GridIMP as part of the wider scheme.
Products & Services
Products
- AlphaESS G3-H30
- 72.3kWh Extension Cabinet
- Total battery capacity: 30kW / 144.6kWh
Services
- BESS supply
- Installation support
- HIAB offloading and placement
Solution
The completed system combines 218kWp of new solar PV with a 30kW / 144.6kWh AlphaESS battery energy storage system. Each partner contributed specialist expertise to the overall solution. SSE Energy Solutions developed the scheme and provides its Building Management Service, Activ8 Energies delivered the solar PV and BESS installation, Immersa supplied and supported the deployment of the battery system, and GridIMP provides advanced BESS optimisation and control. Through GridIMP's optimisation, the battery can be managed to generate greater savings and revenue for St Katherine's School as part of SSE's wider BMS scheme. Rather than treating solar, storage and energy management as separate technologies, the project brings them together as part of one coordinated energy strategy.
Results & Impact
- The project provides St Katherine's School with new renewable generation and flexible battery storage, supported by intelligent energy management
- 218kWp of new solar PV installed
- 30kW / 144.6kWh of battery storage deployed
- Advanced BESS optimisation and control through GridIMP
- Greater opportunity to reduce energy costs and generate additional value
- Integrated into SSE Energy Solutions' Building Management Service
- Successful collaboration between four specialist energy partners
Value Delivered
- St Katherine's School demonstrates the value of collaboration when delivering more advanced commercial energy projects.
- By bringing together SSE Energy Solutions, Activ8 Energies, Immersa and GridIMP, the project combines scheme development, solar PV, battery storage and intelligent optimisation within one solution.
- For Immersa, the project also demonstrates how we can work as the specialist BESS partner within a wider project team, supporting installers and energy service providers with the technology and practical installation support required to deliver successful commercial battery projects.